76 Construction Update: EB lane to close in front of Presley's Theater , EB traffic use center lane

76 Revitalization construction moving to Presley’s Theater:

Beginning today, December 19, construction crews will begin installing new water line and underground utility conduits in front of the Presley’s Theater property at 2920 Highway 76. The EB lane of 76 will be closed, and traffic diverted to the center lane.

Barricades and signs will safely reroute motorists around the construction zone.

This underground installation is expected to take about two weeks to complete.

Approximately 30% of the underground utility installation has been completed in Phase 1A, from Presley’s Theater on the east side of 76 to Ripley’s Believe It or Not museum on the west.